The short answer
A DCR Notice of Deficiency Report or Administrative Order starts a short statutory clock: under Va. Code § 10.1-609 you generally have 30 days to file a corrective action plan prepared by a licensed professional engineer, and a limited window to petition for a hearing. Missing either can lead to civil penalties or a state-directed drawdown of the impoundment.
Talk Through Your DCR Notice or Order
Deadlines under Va. Code § 10.1-609 are short. Speak directly with Jim Lang about your notice, corrective plan, or hearing petition.
Learn more about our Virginia dam safety practice.